Industry Calculator

Calculate manufacturing and reaction costs, time, and profit for any blueprint.

Large Processor Overclocking Unit I Manufacturing

Blueprint Settings

Build Components

No buildable intermediates for this blueprint.

Manufacturing Facility Settings

Total Cost
832,763.57
ISK
Sell Value
1,403,000.00
Profit
+570,236.43
ISK
Margin
40.6%
Build Time
40m 48s
1 run

Materials

3 items
Material Quantity Unit Price Total
40 782,074.00
81 17,082.90
100 30,569.00
Material Total 829,725.90
System Cost Index (0.14%) 102.72
SCC Surcharge (4%) 2,934.95
Job Installation Cost 3,037.67
Grand Total 832,763.57

Production Timeline

d
Assembly 40m 48s
1
Large Processor Overclocking Unit I
Large Processor Overclocking Unit I M
1 job, 1 run 40m 48s/job 40m 48s
Total Wall Clock Time 40m 48s

Required Skills