Industry Calculator

Calculate manufacturing and reaction costs, time, and profit for any blueprint.

Leshak Manufacturing

Blueprint Settings

Build Components

| |

Manufacturing Facility Settings

Total Cost
372,325,986.36
ISK
Sell Value
500,370,588.24
Profit
+128,044,601.88
ISK
Margin
25.6%
Build Time
2h 43m 12s
1 run

Materials

12 items
Material Quantity Unit Price Total
2 6,151,368.06
99 7,976,376.54
198 9,109,958.22
761 38,128,504.76
765 30,631,059.00
6,930 17,131,722.30
13,860 17,922,920.40
41,580 29,179,180.80
396,000 72,127,440.00
594,000 29,177,280.00
3,960,000 73,299,600.00
7,920,000 30,175,200.00
Material Total 361,010,610.08
System Cost Index (0.14%) 382,645.57
SCC Surcharge (4%) 10,932,730.70
Job Installation Cost 11,315,376.28
Grand Total 372,325,986.36

Production Timeline

d
Assembly 2h 43m 12s
1
Leshak
Leshak M
1 job, 1 run 2h 43m 12s/job 2h 43m 12s
Total Wall Clock Time 2h 43m 12s

Required Skills