Industry Calculator

Calculate manufacturing and reaction costs, time, and profit for any blueprint.

Prowler Manufacturing

Blueprint Settings

Build Components

| |

Manufacturing Facility Settings

Total Cost
79,167,040.57
ISK
Sell Value
111,500,000.00
Profit
+32,332,959.43
ISK
Margin
29.0%
Build Time
1d 7h 5m
1 run

Materials

11 items
Material Quantity Unit Price Total
102 3,316,020.00
54 1,047,200.40
Wreathe
1 2,049,938.97
2,700 13,024,260.00
81 1,342,980.00
1,080 40,878,000.00
135 3,253,068.00
102 935,544.00
10 6,396.80
35 4,413,500.00
203 6,087,955.79
Material Total 76,354,863.96
System Cost Index (0.14%) 95,097.76
SCC Surcharge (4%) 2,717,078.85
Job Installation Cost 2,812,176.61
Grand Total 79,167,040.57

Production Timeline

d
Assembly 1d 7h 5m
1
Prowler
Prowler M
1 job, 1 run 1d 7h 5m/job 1d 7h 5m
Total Wall Clock Time 1d 7h 5m