Industry Calculator

Calculate manufacturing and reaction costs, time, and profit for any blueprint.

Capital Turret Hardpoint Manufacturing

Blueprint Settings

Build Components

| |

Manufacturing Facility Settings

Total Cost
8,941,671.26
ISK
Sell Value
12,270,000.00
Profit
+3,328,328.74
ISK
Margin
27.1%
Build Time
2h 25m 4s
1 run

Materials

9 items
Material Quantity Unit Price Total
1 1,975,454.17
90 298,234.80
170 498,236.00
351 506,366.64
675 502,078.50
6,750 1,622,497.50
24,975 93,406.50
25,650 1,477,953.00
91,125 1,665,765.00
Material Total 8,639,992.11
System Cost Index (0.14%) 10,201.71
SCC Surcharge (4%) 291,477.44
Job Installation Cost 301,679.15
Grand Total 8,941,671.26

Production Timeline

d
Assembly 2h 25m 4s
1
Capital Turret Hardpoint
Capital Turret Hardpoint M
1 job, 1 run 2h 25m 4s/job 2h 25m 4s
Total Wall Clock Time 2h 25m 4s

Required Skills