Industry Calculator

Calculate manufacturing and reaction costs, time, and profit for any blueprint.

Archon Manufacturing

Blueprint Settings

Build Components

| |

Manufacturing Facility Settings

Total Cost
1,930,113,908.33
ISK
Sell Value
2,949,000,000.00
Profit
+1,018,886,091.67
ISK
Margin
34.6%
Build Time
11d 8h
1 run

Materials

18 items
Material Quantity Unit Price Total
1 86,200,000.00
1 168,555,555.56
1 731,834,146.34
3 37,260,000.00
3 40,650,000.00
3 38,067,194.25
3 35,904,793.38
3 40,650,000.00
4 52,560,000.00
4 39,770,054.04
4 72,810,126.60
4 33,257,620.96
6 104,040,000.00
6 95,640,000.00
11 67,100,000.00
11 191,290,000.00
180 14,569,506.00
360 16,574,310.00
Material Total 1,866,733,307.13
System Cost Index (0.14%) 2,143,305.35
SCC Surcharge (4%) 61,237,295.85
Job Installation Cost 63,380,601.20
Grand Total 1,930,113,908.33

Production Timeline

d
Assembly 11d 8h
1
Archon
Archon M
1 job, 1 run 11d 8h/job 11d 8h
Total Wall Clock Time 11d 8h

Required Skills