Industry Calculator

Calculate manufacturing and reaction costs, time, and profit for any blueprint.

Standup Einherji I Manufacturing

Blueprint Settings

Build Components

No buildable intermediates for this blueprint.

Manufacturing Facility Settings

Total Cost
7,413,458.94
ISK
Sell Value
12,600,673.58
Profit
+5,187,214.64
ISK
Margin
41.2%
Build Time
1h 17m 32s
1 run

Materials

7 items
Material Quantity Unit Price Total
378 934,457.58
495 640,104.30
900 631,584.00
13,500 2,458,890.00
15,750 773,640.00
54,000 999,540.00
175,500 668,655.00
Material Total 7,106,870.88
System Cost Index (0.14%) 10,367.71
SCC Surcharge (4%) 296,220.35
Job Installation Cost 306,588.06
Grand Total 7,413,458.94

Production Timeline

d
Assembly 1h 17m 32s
1
Standup Einherji I
Standup Einherji I M
1 job, 1 run 1h 17m 32s/job 1h 17m 32s
Total Wall Clock Time 1h 17m 32s

Required Skills