Industry Calculator

Calculate manufacturing and reaction costs, time, and profit for any blueprint.

Large Industrial Core II Manufacturing

Blueprint Settings

Build Components

| |

Manufacturing Facility Settings

Total Cost
53,532,719.33
ISK
Sell Value
76,790,000.00
Profit
+23,257,280.67
ISK
Margin
30.3%
Build Time
15h 54m 44s
1 run

Materials

7 items
Material Quantity Unit Price Total
1 24,986,451.61
225 3,375,533.25
225 9,122,238.00
450 3,654,450.00
450 9,678,942.00
450 185,175.00
450 1,491,124.50
Material Total 52,493,914.36
System Cost Index (0.14%) 35,128.67
SCC Surcharge (4%) 1,003,676.30
Job Installation Cost 1,038,804.97
Grand Total 53,532,719.33

Production Timeline

d
Assembly 15h 54m 44s
1
Large Industrial Core II
Large Industrial Core II M
1 job, 1 run 15h 54m 44s/job 15h 54m 44s
Total Wall Clock Time 15h 54m 44s

Required Skills